Day 5 with No Water: Hurry Up and Wait

The Trench taped off to wait for the city inspector in the morning.
The Trench taped off to wait for the city inspector in the morning.

Today was to be the day we got our water back. We hired the company R Mech to replace the water line between the water main and the house. They had the lowest bid, along with the best detail in their bid about the work they would be doing. And they arrived promptly on Monday morning, as they said they would.

Tim digging the trench.
Tim digging the trench.

I had wondered how they were going to get the equipment up to the front lawn: we have a 45% slope in front, and steps up the side. When they arrived and unloaded the backhoe they showed me how: drove it all the way up the driveway, and around the back and side of the house to get to the front. All he had to do was very adroitly move a couple three edging stones I had placed at the back of the driveway over the years.

The trench ffrom a road view.
The trench ffrom a road view.

I had wondered, and been concerned, about where the pipe entered the basement. We could see the pipe coming into the basement from the inside, but I did wonder where outside that might be.  It had the possibility of going right underneath the front step.  But after careful measurements by the R Mech crew — Tim and Paul — they confirmed that it went in just to the side of the step. So they started digging the trench.

The trench with the old water line still in it.
The trench with the old water line still in it.

It was a rather impressive show to see how swiftly, and with what precision, Tim operated the backhoe. His 40 years of experience was obvious in the clean way he cut the trench, and the delicate way he worked along the wall of the house and cut down to the old water line without abrading it.

The trench was dug by 11:30, and the new pipe and meter pit laid and installed by noon. Then it was sitting around and waiting for the city inspector to arrive and install the water meter. I watched Paul and Tim waiting around, Tim on the phone again and again to the inspector, until it was finally confirmed that the inspector would not be coming today, but tomorrow morning.

The trenche with the new water line in it.
The trenche with the new water line in it.

During the morning and early afternoon I took a couple of minutes every hour to check on the progress, and see how it was going.  I learned a lot in those rare minutes, talking to Paul, and then Tim, about our project and the principles of their work. As usual, I was both impressed and amazed by the knowledge and skills of these craftsmen.

The new water connected to the water main.
The new water connected to the water main.

Tomorrow:  Water Finally! (we hope)

Roll of copper pipe in the trench.
Roll of copper pipe in the trench.
Paul and Tim measuring for the Meter Pit.
Paul and Tim measuring for the Meter Pit.
Tim and Paul installing the meter pit.
Tim and Paul installing the meter pit.
The new water line leading into, and out of, the meter pit.  All it needs now is a meter.
The new water line leading into, and out of, the meter pit. All it needs now is a meter.
The new pipe and valve being connected in the basement by Paul.
The new pipe and valve being connected in the basement by Paul.
The new water line leading into, and out of, the meter pit.  All it needs now is a meter.
The new water line leading into, and out of, the meter pit. All it needs now is a meter.

 

 

 

 

3 thoughts on “Day 5 with No Water: Hurry Up and Wait

      1. You’re most welcome. I understand all about being without water, and it’s not any fun at all. You and your family have done very well dealing with this challenge.

        Like

Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.